Client: |
Messina Platinum Mines Ltd |
Location: |
Polokwane, South Africa |
Period: |
2001 |
Scope: |
Mine plant with associated infrastructure |
DRA Global was approached to develop the Voorspoed project, part of a four-phase development of the Messina platinum mine. Client required an interim 30 ktpm concentrator to be built in record time.
DRA was expected to complete the project, from initial design to final commissioning in 5 months – a process that normally takes 12 to 16 months. The project’s timeline constraints necessitated innovative methods. DRA sourced and refurbished a number of key plant components. Steel fabrication was accelerated by sourcing ad coordinating the effort of 11 fabricators, delivering and erecting the steel in sequence while ensuring quality at every stage and eliminating double handling.