Projects

Ahafo Gold Project

Client:

Newmont Goldcorp

Location:

Ghana

Capacity:

3.5 MTPA

Value:

USD 151.5 million

Scope:

EPCM for Gold concentrator and associated infrastructure

Period:

2014 - 2016

DRA Global was awarded the EPCM contract for the Ahafo Mill Expansion Project (AME) located in Ghana, owned by Newmont.

DRA delivered the Trade-off, Prefeasibility and Bankable Feasibility Studies from 2014 to 2016.

The AME project expands the existing plant by 3.5 MTPA through installation of a new primary gyratory crusher, a single stage duel pinion 13MVA SAG mill and three additional leach tanks, together with an additional tailings line and pump system.

DRA is poised to start with the execution phase during Q4 2016 with detail engineering and procurement setup continuing.